6/14/08 We take a look at the recreation area progress for the week

Fencing for the tennis area arrives on site

The picnic area circle outer edge is poured

The gas grills will be on the outside of the circle

The shuffleboard area gets attention

Looking from the tennis court toward the basketball & pond

The electrical work continued as well

Gravel gets final preparation prior to concrete - basketball area

Concrete poring for sidewalk to picnic area

First section of basketball court gets its concrete

Covered as there is a threat of a storm

Picnic area center also poured and covered

Look closely and you'll see the fence posts for the tennis court (green)

View from picnic area back over tennis court to left - shuffleboard on right

Scheduled for next week: Remaining basketball concrete, all of the tennis court concrete.

See previous Photos