3/3/07 This weeks progress

Concrete sidewalks have been poured and cured

Fencing starts to go back up

Public sidewalk on Lake St side is in place

Cement base for driveways arrives

View down the public sidewalk looking at the driveway exit

Entrance to new driveway with concrete base material

West side of building by pool. New sprinkler piping laid out

Paving due soon. Final step will be the landscaping work.

The roofing project heads into its final stages as the last three buildings are well under way.

This is building 7, the largest building on property being stripped of tile

The new underlayment is rolled out

At building 5 the metal surface is moving along well

Some areas of Building five already have the finish parts in place

Building 6 is also in the process of tile removal

A view of the finished product on Building 2. It is complete.

Building 1 (as well as 3,4 and 8) are also completed and accepted

Building 3 as finished

Another view of Building 2

 

Building 4 pool side

Building 5 from the Clubhouse view still underway

Building 6 from the Clubhouse side with new underlayment in place

Moving to the Lobby work. The new lighting is installed

Behind the front desk area

Near the fish tank

One of the lobby seating areas

We hope to have some wider angle photos of the finished lobby soon.

Much more to come. Check back frequently.

See 2/22/07 Photos