• 09/11/12 – Work continues on the ADA remediation at the Clubhouse – Photos from 9/7/12
  • The reinforced footings are prepared
  • There are 4 total – one in each corner of the portico canopy
  • All construction is inspected and approved by the County
  • Construction supplies, waste container and equipment on site
  • Frame for concrete pour is under construction
  • View from Clubhouse entry out to Flag Island
  • Massive mounts to be set in concrete for steel pavilion supports
  • More progress on 9/11/12
  • Finished, inspected footers await concrete pour
  • New structure will extend the original small covered entry over the new paver driveway
  • After footers are completed the new grade will be established and reconfigured sidewalks poured.
  • 9/12/12 UPDATE:
  • The footings in, the first steel rises!
  • The portico will have a full 13′ clearance to help prevent any accidental impacts
  • The roof drains will be concealed inside the pillars for a clean appearance
  • The driveway width will be the same as before despite the wider sidewalk
  • View from entryway to Flag Island with the base steel frame in place
  • Update 9/21/12 – Rain has delayed progress but here are two updated photos from Monday:
  • The front entry by doors awaits the new ADA approved, non-slip pavers
  • The framing for the Portico roof is under construction. Total project remains on schedule.
  • Much more to come. Check back to see progress pictures.